Preconstruction — Estimating & Cost

Unit Price Contract

Pricing work by the measured unit when the total quantity isn't known yet.

Quick Answer

A unit price contract pays the contractor a fixed rate for each measured unit of work — per cubic yard of excavation, per linear foot of pipe — rather than one lump sum. Final payment is the unit rate times the quantity actually installed. It fits work where the scope is clear but the total quantity can't be known until the work is done.

The Full Picture

Unit pricing exists for the gap between 'we know what the work is' and 'we don't yet know how much of it there'll be.' Earthwork, utilities, paving, and site remediation are classic cases: the design defines the work precisely, but the true quantity depends on conditions that only reveal themselves during construction.

Mechanically, the owner provides estimated quantities for each work item, contractors bid a unit rate against each, and the bid total is the sum of rate times estimated quantity. During construction, actual installed quantities are measured — 'remeasured' — and the contractor is paid the agreed rate times the real quantity. The rate is fixed; the quantity floats.

This structure shifts quantity risk to the owner and keeps productivity risk with the contractor. If more excavation is needed than estimated, the owner pays for the extra units at the pre-agreed rate — no renegotiation, no change order for the quantity itself. That predictability on rate is why public agencies use unit prices heavily for infrastructure and site work.

The discipline in preconstruction is accurate measurement and honest unit rates. Contractors sometimes 'unbalance' a bid — loading rates on items likely to overrun and shaving items likely to underrun — so owners scrutinize unit-rate reasonableness, not just the bottom line. Clean quantity takeoffs on both sides keep the remeasurement honest.

Real Examples

Earthwork: A site contract bids $18 per cubic yard for excavation against an estimated 40,000 CY; the contractor is ultimately paid for the 43,500 CY actually removed at that same rate.
Utilities: Storm pipe is priced per linear foot, so when field conditions require a longer run than drawn, payment adjusts automatically without a change order for the added length.
Unbalanced bid: A reviewer flags that a contractor's excavation rate is far above market while backfill is far below — a sign the bid is loaded toward an item expected to overrun.

Common Misconceptions

People assume: A unit price contract means the total cost is unknown until the end.

Actually: The rates are fixed and the owner has estimated quantities, so a reliable projected total exists from day one. Only the final reconciliation moves, and it moves predictably at agreed rates — not through open-ended negotiation.

People assume: Unit price contracts remove all cost risk for the owner.

Actually: They fix the rate but leave quantity risk with the owner. If actual quantities balloon, so does the owner's cost. Owners manage this with careful quantity estimates and scrutiny of unbalanced unit rates.

Does MeltPlan Solve This?

Partially — adjacent

Unit price bids stand or fall on quantities, and MeltPlan produces verified quantity takeoffs from your drawings — the measured basis for both bidding unit rates and checking remeasurement. It doesn't set unit rates or administer the remeasurement itself, but it gets you accurate quantities to price against far faster than manual takeoff.

Get verified quantities to price unit rates against

Frequently Asked Questions

When is a unit price contract used?

When the type of work is well defined but the total quantity isn't known until construction — earthwork, utilities, paving, remediation. It's especially common on public infrastructure where quantities depend on field conditions.

How is a unit price contract paid?

The contractor is paid the fixed unit rate times the quantity of work actually installed, measured during construction. The rate is locked at bid; the quantity is reconciled through remeasurement.

What is an unbalanced bid?

A tactic where a contractor inflates unit rates on items likely to overrun and lowers rates on items likely to underrun, aiming to earn more than the bid total implies. Owners review unit-rate reasonableness to catch it.

What's the difference between unit price and lump sum?

A lump sum is one fixed price for a defined scope, with the contractor carrying quantity risk. A unit price fixes only the rate per unit and pays for actual measured quantities, leaving quantity risk with the owner.

Related Terms

More Preconstruction — Estimating & Cost Terms

Sources

  1. Federal Highway Administration (FHWA) — Construction contract administration guidance
  2. AGC of America — Construction contract documents & delivery
MELTPLAN