Air Handling Unit (AHU)
The central HVAC unit that filters, heats or cools, and moves a building's air.
Quick Answer
An air handling unit (AHU) is a factory-built HVAC unit with a casing holding a fan, filters and heating or cooling coils, which conditions air and pushes it through ductwork. On plans it appears as a tagged item such as AHU-1. Estimators count it each (EA), sized by airflow in CFM and capacity in tons.
The Full Picture
An air handling unit is the machine at the center of an air-based HVAC system. One university construction standard describes a casing containing a fan, a filter and cooling, heating and/or humidification coils, with mixing boxes, return fans and damper sections added as needed. Return air and outdoor air come in, the unit conditions the mix, and the supply fan sends it out through ducts to diffusers, VAV boxes or other terminals. The same standard notes that units installed inside are typically called AHUs, while exposed units on a roof are rooftop units (RTUs). Many AHUs are chilled-water and hot-water units fed by a central plant, so the unit sits at the end of piping that is priced separately.
On the drawings an AHU is tagged and located on the mechanical floor plan or roof plan, shown with its duct connections, and described in the equipment schedule on the mechanical schedule sheets. A typical schedule row gives the tag, the area served, supply airflow in CFM, outside air CFM, fan motor size, coil capacities, filter type, electrical characteristics and the weight. Division 23 of the specifications covers the unit itself, and Duke's standards, for example, file it under 23 70 00 Central HVAC Equipment. Cooling capacity is often shown in tons, and one ton is 12,000 Btu of cooling.
The takeoff unit is each (EA), one per tag, and the price depends on what the schedule says. Airflow and coil capacity drive the size of the unit, and filter sections, energy recovery, a return fan, a VFD, sound attenuation and a custom casing all change the price. An estimator therefore pulls the schedule row into the carry sheet rather than counting a symbol alone. Items attached to the unit are usually separate lines: the concrete pad or steel dunnage, vibration isolation, chilled and hot water piping connections with valves, condensate drain, electrical feed and disconnect, controls, and startup and balancing.
Pricing mistakes tend to come from the edges. Equipment is often furnished by one party and set by another, so a missing crane or rigging line is a common gap, particularly for units delivered in sections. Another is counting every AHU on the schedule when one is noted as existing or by owner. A third is pricing the unit from the plan view alone when the schedule calls for a larger fan, a different coil or an energy recovery section. Ductwork leaving the unit is its own takeoff and bid package, and the controls are usually carried by a specialty contractor.
Real Examples
Common Misconceptions
People assume: An AHU and a rooftop unit are the same thing.
Actually: Both condition and move air, but one university standard distinguishes units installed inside (AHUs) from exposed rooftop units (RTUs). Rooftop units are often packaged with their own cooling and heating, while many AHUs use chilled and hot water from a central plant, which changes the piping scope.
People assume: The AHU price includes everything needed to make it run.
Actually: The equipment price is the unit as scheduled. Pads, rigging, piping connections, electrical, controls, ductwork and balancing are usually separate lines or separate trades, and each is a place where scope can fall between bids.
Does MeltPlan Solve This?
Partially — adjacentCounting AHUs and tying each tag to its schedule row is a takeoff task, and MeltPlan's takeoff service has AI pull quantities from plans with US-based experienced estimators reviewing and adjusting them. Equipment selection, vendor pricing and the allowances for rigging and controls stay with your estimating team.
Get mechanical equipment counted from your plans →Frequently Asked Questions
What does an air handling unit do?
It draws in return air and outdoor air, filters it, heats or cools it with coils, and pushes it through ducts to the spaces served. Some units also humidify or recover energy. It is the main air mover in a central air system.
How is an AHU counted in a takeoff?
Each (EA), one per equipment tag on the schedule. The estimator records CFM, tons or coil capacity, and options such as a return fan, VFD or energy recovery section, because they change the price. Connections and accessories are carried on separate lines.
What is the difference between an AHU and an RTU?
An AHU is generally an indoor unit, often served by chilled and hot water. An RTU is a packaged unit set on the roof. One university standard separates the two this way. Both appear on the mechanical equipment schedule.
Where is the AHU shown on the drawings?
It is tagged on the mechanical floor or roof plan, detailed on the schedule sheet with its CFM and capacities, and described in a Division 23 specification section. Always compare the plan tag against the schedule row.
How does tonnage relate to AHU size?
Cooling capacity is commonly stated in tons, where one ton equals 12,000 Btu of cooling. The schedule usually lists airflow in CFM as well, so a unit is described by both numbers.